Center collar placement – Grain Systems Tanks PNEG-4135 User Manual

Page 120

Advertising
background image

Chapter 7: Roof Assembly

Center Collar Placement

The following figure gives the approximate height needed to install the center collar.

With two sidewall rings in place, position the center collar at the height specified, measuring from the
bottom of the center collar to the foundation as shown. If additional rings are required for construction pur-
poses, add 32 in. for each additional ring.

NOTE: It is better to set the center collar a little too high. Do not set the center collar too low.

Figure 7-33 Center collar placement

A

473.35 in. (1202.31 cm) from foundation to bottom of center collar on 135 ft diameter bin

120

Pneg-4135 135 Ft Diameter 40-Series Bin

Advertising