Chapter 7: Roof Assembly

Figure 7-45 Installing the first upper roof panel

C

Upper roof panel (CTR-0337)

E

5/16-18 x 1 flange bolt with sealing washer (S-
10260)

D

Middle roof panel (CTR-0343)

F

5/16 in. flange nut (S-3611)

15.With assistance, position the adjacent upper roof panels (C) overlapping the previous upper roof

panels.

16.Install flange bolts (E) and flange nuts (F) to secure the overlapping panels as shown.