Chapter 7: roof assembly – Grain Systems Tanks PNEG-4135 User Manual

Page 139

Advertising
background image

Chapter 7: Roof Assembly

Figure 7-49 Lifting the center collar channel and cap plates

A

Tube caulk

D

Cap plate assembly, approximately 1700 lb
(771.1 kg)

B

Appropriate lifting chains

E

1/2 x 1-3/4 in. flange bolt (S-10252)

C

Appropriate lifting device

F

1/2 in. nut (S-10253)

8. Secure the cap plate assembly to the center collar using bolts with sealing washers (G) and nuts (H),

leaving the peak conveyer support bracket holes (I) unfilled.

9. Replace the six vendor eyebolts with the supplied bolts with sealing washers (G) and nuts (H).

10.Tighten all hardware to the recommended torque specifications. See

Bolt Torque Specifications,

page 26

.

Pneg-4135 135 Ft Diameter 40-Series Bin

139