Rack and pinion installation (8" and 10" systems) – Grain Systems Unload Augers PNEG-1421 User Manual
Page 24
Advertising
![background image](/manuals/277898/24/background.png)
4. Installation
24
PNEG-1421 Direct Gear Drive Bin Sweep Auger (with Roller Wells)
Rack and Pinion Installation (8" and 10" Systems)
1. Make sure all gates are fully closed.
2. Slip rack and pinion tube over center gate control rod and align holes, making sure rack and pinion
is fully extended toward bin wall.
3. With rack and pinion resting on unload tube and tube holes aligned, insert one 5/16" x 1-3/4"
bolt through the rack and pinion tube and center gate control rod. Fasten together with a nut.
Figure 4P 8" and 10" Systems
Advertising