GE Industrial Solutions Millennium II Controller J85501P-1 User Manual
Page 89

Basic Installation and User’s Guide for the Millennium II Controller
Issue 3 January 2008
89
7.
Securing Contactors
If Battery and Load contactors are in the system, contactor control boards
should be configured so that they do not OPEN during the controller
replacement. To ensure that these contactors do not open, force all LVLD
and LVBD contactors closed.
NOTE: These contactors may have already been forced closed per
customer requirements. If so, then proceed to the next step.
To force LVLD contactors closed, place SW300 in the up position as
shown in figure 6-2 and 6-3.
Contactor Type
Control Board and
Switch
To Force Closed,
Change to
Load
EBV – SW300
UP
Battery
BJN – SW300
UP for ½ height
cabinets
DOWN for full
height cabinets
8.
Disconnect Rectifiers from Old Controller
The RJ45 connector is located at top of the BSH board. Remove the
cable connected to J8.
(see Figure 6-10)
Step Action
a.
On the Basic controller (BSH), locate J8.
b.
Mark, Tag and Insulate the cable terminating at J8.
This is the Rectifier Control Cable.
c.
Remove this cable from J8 and take it out of the
Millennium housing.