Maintenance

NOTE

To ensure the continued safety and

efficiency of the boiler, the sched-

ule of maintenance outlined in this

section should be adhered to.

WARNING

Prior to the commencement of any

work requiring the removal of cover

plates and the opening of the con-

trol panel box, the electrical supply

to the boiler must be disconnected.

Procedure for Cleaning Water

Probes

Clean probe on top of boiler shell

and probes in water column. Make

sure there is no pressure on the

boiler during the removal of the

probes. Remove one probe (using

a 7/8" socket), clean with very fine

emory cloth and replace it before

removing another to assure no

probe mix-ups that would change

the control functions.

For replacement purposes, installed

probe lengths are indicated in the

chart below. For a universally adapt-

able plug and probe which can be cut

to length in the field to fit all boilers,

order Part No. 2-20-017.

*A = 7-1/4” -- 184 mm
*B = 9-1/4” -- 235 mm
*C = 11-1/4” -- 286 mm

D = 17-1/8” -- 435 mm

*For 4 HP boilers only, water column

probes are 2” shorter.