Changing the Valves and Peak Information

The valve on/off timing set in the analyzer can be changed. The individual information (peak

names, gate time, etc.) set for each peak also can be changed. This section explains how to

change these settings.

NOTE

The valve and peak information can be changed only at user level C. This change cannot be

made unless the analyzer is in the Remote mode.

n

Changing the Valve On/Off Setting

(1) Click on the [Valve] command in the [Set Up] menu.
(2) The Valve on/off dialog box pops up.

F0330.ai

Specify the valve number you want to change. The information of the current state is

displayed.

(3) Change the on/off times of the valves, and then click on the [Execute] button. A confirmation

dialog box pops up.

F0331.ai

(4) Click on the [Yes] button.
(5) A message appears to inform you that the data has been changed successfully.

F0332.ai

(6) Click on the [OK] button to finish.