7

Commissioning

Initial switch−on

EDKMF2178IB DE/EN/FR 6.0

70

l

H2_FirstOn−LEDs_KommModul_BT

Initial switch−on

)

Note!

Follow the commissioning steps in the given order!

1. Switch on the standard device and, if necessary, the external voltage supply of the

communication module.
– The green LED

0 on the front of the communication module is lit.

– The status LED of the standard device (Drive LED)

2 must be lit or blinking. The

meaning of the signalling can be found in the standard device documentation.

2. You can now communicate with the drive, i. e.

– all parameters (SDO) can be read;
– all writable parameters (SDO) can be overwritten.

3. After a state change ("Operational") process data can be exchanged with the drive.

2172CAN000D

Fig. 7

LEDs of the communication module