Commissioning, 6commissioning – Lenze 931W User Manual

Page 37

Advertising
background image

Commissioning

Before switching on

Voltage supply connection

6

37

GHB 13.0002-EN 3.1

6

Commissioning

6.1

Before switching on

Stop!

Avoid injury to persons and damage to material assets during commissioning!

ƒ

Necessarily observe the switch-on sequence.

ƒ

During the resolver adjustment, the drive has to be able to rotate freely

without load!

Tip!

For faults during commissioning, see chapter Troubleshooting and fault

elimination. ( 45)

Checking of electrical connections
Before the first commissioning, before commissioning after longer downtimes, check:

ƒ

the electrical connection with regard to completeness, short circuit and earth fault.

ƒ

All plugs on the controller must be securely connected using the screw and plug

connections provided.

ƒ

The screw connections on the motor must be securely connected.

ƒ

Carefully check the connections to the supply system and ensure that the

current-carrying connections are correct.

ƒ

24 V and 42 V controllers require correspondingly high currents to reach their

maximum performance.

6.1.1

Voltage supply connection

ƒ

Ensure correct pole connections (extra-low voltage or mains voltage) for feeding the

voltage supply (extra-low voltage)!

ƒ

Ensure that auxiliary supply (24 V for control) and supply voltage (24 V or 42 V

DC-bus supply) are separately connected. When the supply is mixed up, the servo

inverter may be destroyed.

6.1.2

Motor connection

ƒ

For trouble-free operation, we recommend to use Lenze standard cables.

ƒ

Ensure a proper shielding of the motor and feedback cable to avoid interferences.

Advertising