INSTALLATION PROCEDURES

B. Opening Power Supply Enclosure

The left side panel (viewed from the front) of the Power Supply
must be removed to make electrical connections and to select
the proper input voltage.

WARNING

Disconnect primary power at the source before
assembling or disassembling power supply, torch
parts, or torch and leads assemblies.

1. Remove the ten screws which secure the left side panel

(viewed from the front) to the Power Supply .

Left Side Panel

Screws

(10 Places)

A-01535

Figure 3-3 Opening Power Supply

2. Remove the left side panel from the Power Supply.

3.07 Checking Input Connections

The Power Supply is wired to use input voltages of
380/415 VAC. Internal busbars must be checked on the
input voltage terminal board to verify proper installation
.

1. Locate the input voltage terminal board on the

left side of the power supply.

Input Voltage

Terminal Board

L1

L2

L3

Busbars

A-01091

Extra Busbar

Storage Location

Figure 3-4 Input Voltage Terminal Board Location

NOTE

Extra busbars are attached (stored) to the top
side of the power transformer assembly.

2. Check the busbar configuration on the input voltage

terminal board . The busbar configuration must corre-
spond with the available line voltage per the following
figure and the label inside the unit:

11

12

L3

13

15

14

6

7

L2

8

10

9

1

2

L1

3

5

4

Busbar Connections

For Input Voltage

Of 380/415 VAC

A-01090

Figure 3-5 Busbar Connections

If necessary, reposition the busbars to correspond to the
available line voltage.