Appendix 12: routine maintenance schedule – Tweco 6000 CE Merlin User Manual

Page 72

Advertising
background image

APPENDIX

A-14

Manual 0-2601

APPENDIX 12: ROUTINE MAINTENANCE SCHEDULE

This recommended schedule applies to all types of liquid cooled plasma cutting systems. Some systems will not
have all the parts listed and those checks need not be performed.

NOTE

The actual frequency of maintenance may need to be adjusted according to the operating environment.

Daily Operational Checks or Every Six Arc Hours:

1. Check torch parts, replace if damaged.

2. Check plasma and secondary supply and pressure/flow.

3. Purge plasma gas line to remove any moisture build-up.

4. Check deionizer bag/cartridge, replace if color is predominantly yellow.

5. Check coolant pressure (100 - 120 psi).

Weekly or Every 30 Arc Hours:

1. Check fan for proper operation and adequate air flow.

2. Blow or vacuum dust and dirt out of the entire machine.

CAUTION

Do not blow air into the power supply during cleaning. Blowing air into the unit can cause metal particles to
interfere with sensitive electrical components and cause damage to the unit.

Six Months or Every 720 Arc Hours:

1. Remove and clean in-line filter screens.

2. Check cables and hoses for leaks or cracks, replace if necessary.

3. Check all contactor points for severe arcing or pits, replace if necessary.

4. Check all pillow blocks and bearings, clean and lubricate if necessary.

5. Check fan, pump and pulley belts for wear or cracking, replace if necessary.

Twelve Months or Every 1500 Arc Hours:

1. Drain coolant, fill with distilled water, turn on main power switch and let machine run for approximately 30

minutes.

WARNING

DO NOT energize the Torch.

Drain distilled water and replace with Thermal Arc Coolant. Use 'Extra-Cool

TM

' Coolant (Catalog # 7-3580) or

'Ultra-Cool

TM

' Coolant (Catalog # 7-3581) for environments below +10° F (-12° C).

2. Check radiator fins, clean and comb out if necessary.

3. Repeat six month maintenance.

Advertising