FIELD PREPARATION

SETTING OVERLAP

An automatic delay or advance can be configured to enable and disable

planter sections when approaching or leaving an area by setting a Run In/

Run Out Overlap or Skip and a side-to-side overlap. A distance is entered in

inches/metric to enable this feature.

RUN IN OVERLAP

A Run In Overlap sets the distance (inches) to automatically delay section

shutoff when a planted area is entered.

RUN OUT OVERLAP

A Run Out Overlap sets the distances (inches) to automatically turn on

sections before a planted area is exited.

RUN IN SKIP

A Run In Skip sets the distance (inches) to automatically shutoff sections

before a planted area is entered.

RUN OUT SKIP

A Run Out Skip sets the distance (inches) to automatically turn on sections

after a planted area is exited.

SIDE-TO-SIDE OVERLAP

When entering an angled headland, a side-to-side overlap defines the

percent of overlap to occur when the angle is crossed. A percentage

adjustment between 50% to 100% in increments of 10% is allowed. At

100%, the shutoff and turn on point is calculated as each section reaches

the angle. At 50%, the shutoff and turn on point is calculated as each

section middle crosses the angle. (

Figure 29

) illustration depicts a planter

configured as one entire section with a 50% and 100% overlap.