Carrier WEATHER MASTER 48P2 User Manual

Page 2

Advertising
background image

2

INSTALLATION

Step 1 — Perform Jobsite Survey —

Complete

the following checks before installation.

1. Consult local building codes and the NEC (National

Electrical Code) (ANSI/NFPA [American National Stan-

dards Institute/National Fire Protection Association] 70)

for special installation requirements.

2. Determine unit location (from project plans) or select unit

location.

3. Check for possible overhead obstructions which may in-

terfere with unit lifting or rigging.

Step 2 — Place Unit —

Inspect unit for transportation

damage. File claim with transportation agency.

Provide clearance around and above unit for airflow, safety,

and service access. Do not restrict top (area above condenser

fans) in any way. Allow at least 6 ft on all sides for rated perfor-

mance, code compliance, and service. On units equipped with

power exhaust option, high velocity air is exhausted out the

hood. Unit should be positioned with at least 10 ft clearance be-

tween the exhaust hood and any obstruction.

Check unit dimensional drawings for unit arrangement and

minimum performance and service clearances.

Do not install unit in an indoor location. Do not locate air in-

lets near exhaust vents or other sources of contaminated air.

Although unit is weatherproof, guard against water from

higher level runoff and overhangs.

Level by using unit frame as a reference. Physical data is

shown in Tables 1A-9.

Step 3 — Roof Mount Unit —

Check building codes

for weight distribution requirements. Unit weight is shown in

Tables 1A-1C and 5. Unit may be mounted on class A, B, or C

roofing material.
ROOF CURB — Assemble and install roof curb as described

in instructions shipped with the accessory. Accessory roof curb

and information required to field fabricate a roof curb is shown

in Fig. 1-5. Install insulation, cant strips, roofing and counter

flashing as required. For unit condensate drain to function

properly, curb must be level or within tolerances shown in

Fig. 1-5.
STEEL BEAMS — If roof curb is not used, support unit with

steel beams along its entire length and then support steel as re-

quired. As a minimum, unit must be supported across its width

at each lifting lug location.

Step 4 — Slab Mount Unit —

Provide a level con-

crete slab that extends beyond unit cabinet at least 6 inches.

Make a slab 8 in. thick with 4 in. above grade. Use gravel

apron in front of condenser coil air inlet to prevent grass and

foliage from obstructing airflow. Ensure that slab is of

sufficient height to allow for condensate trap of 4 in. on sizes

030-070 or 7 in. on sizes 075-100.

Step 5 — Install Curb Gasketing

SIZE 030-060 UNITS — After ductwork has been connected

to the roof curb, attach adhesive-backed gasketing on all end

rails, cross rails, and duct rails. Be sure all joints and corners of

gasket are square and flush to prevent possible water leaks.

Follow all applicable building codes.
SIZE 070-100 UNITS — After ductwork has been connected

to the roof curb, apply gasket material (

1

/

2

-in. thick x 1

1

/

2

-in.

wide neoprene) where indicated.
Single-Thickness Gasketing (See Fig. 6-8 for Item Num-

bers) — Apply gasketing in the following places:

1. Along both side rails (1) — 2 places, full length
2. Along return air end rail (2) — 1 place
3. Around return air internal duct flange (3) — 1 or 2 places
4. Around supply air internal duct flanges (4) — 3 places

Double-Thickness Gasketing (See Fig. 6 and 8 and Detail

A-A) — Locate a line 9

3

/

4

-in. from the supply air end of the

accessory curb. Apply a double-thickness of gasket material

along line per detail A-A.
NOTE: Do not apply gasket material along the outside edge of

the curb (area “X”). This pan area of the curb extends out

beneath the end of the unit’s air handler section; applying gas-

ket here develops a potential water trap area on top of the curb.
Condenser Section Roof Curb (See Fig. 7) — Apply single-

thickness gasket along both side rails (5).

Step 6 — Install Field-Fabricated Ductwork

The 48P2,P3 units are designed for vertical supply/return

only. Field-fabricated ductwork must be attached to the roof

curb, or to the support steel, prior to the final rigging and instal-

lation of the unit. Supply and return duct dimensions are shown

in Fig. 1-3.

To attach ductwork to roof curb, insert duct approximately 10

to 11 in. up into roof curb. Connect ductwork to 14-gage roof

curb material with sheet metal screws driven from inside the duct.

Secure all ducts to the building structure, using flexible duct

connectors between roof curbs and ducts as required. Ducts

passing through an unconditioned space must be insulated and

covered with a vapor barrier. Outlet grilles must not lie directly

below unit discharge.

Design supply duct strong enough to handle expected static

pressures.

Step 7 — Rig Unit —

Do not drop unit; keep upright.

Use spreader bars over unit to prevent sling or cable damage.

Sheets of plywood placed along the condenser coils will pro-

vide additional protection. All lifting lugs MUST be used when

lifting unit. Level by using unit frame as a reference. See Fig. 9

and 10 for information. Unit and accessory weights are shown

in Tables 1A-1C and 5. Weight distribution and center of gravi-

ty can be found in Fig. 11.

CAUTION

Disconnect gas piping from units when leak testing at pres-

sures greater than 0.5 psig. Pressures greater than 0.5 psig

will cause gas valve damage resulting in a hazardous

condition. If gas valve is subjected to pressure greater than

0.5 psig, it must be replaced. When pressure testing field-

supplied gas piping at pressures of 0.5 psig or less, the unit

connected to such piping must be isolated by manually

closing the gas valve.

CAUTION

Do not lift unit with forklift truck. Move unit with over-

head rigging only.

WARNING

For vertical supply and return units, tools or parts could

drop into ductwork and cause an injury. Install a 90-degree

elbow in the supply and return ductwork between the unit

and the conditioned space. If a 90-degree elbow cannot be

installed, then a grille of sufficient strength and density

should be installed to prevent objects from falling into the

conditioned space. Failure to follow these instructions

could result in personal injury or property damage due to

falling objects.

Advertising
This manual is related to the following products: