Byron Jackson Double Mechanical Seal Submersible Pumping Unit • 1042.293/9 • June

04

Page 31 of 68

c.

Install the pipe using chain tongs.

Figure 15 shows the proper method of
applying chain tongs to the flange.

Thereby most of the force is exerted on
the upper flange rather than the on the
discharge housing or the non-return
valve.

Apply torque approximating the values
given in Table 5.

CAUTION The discharge section may require

modification to provide protective
clearance to the flat cable and
splice which will be mounted later
on the riser pipe just above the
pump.

Figure 15 Proper method of applying chain tongs


Pipe Torque

Torque

Size [Nm] [ft-lbs]

2-1/2

620

500

3

950

700

4

1

220 900

5

1

425 1

050

6

1

625 1

200

8

2

170 1

600

10

2

710 2

000

12

4

070 3

000

Table 5

Torque for riser pipe assembly

3. Mount the first length of the riser pipe, which

should not be longer than 0.5 m, onto the as-
sembled pump bowl assembly.

4.

Remove the cable clamps or cable guard from
the pump bowl assembly.

5.

Remove the cloth from the coupling.

6.

Lift the pump bowl assembly above the motor.

7. Check the end float settings that are pre-

adjusted by Flowserve.