2-14

edge switch 2/32 installation guide

Installing and Configuring the Edge Switch 2/32

Task 8: Verify Switch-to-HAFM Server Communication

Communication must be verified between the switch and the HAFM server (High
Availability Fabric Manager
and Product Manager applications). To verify
switch-to-server communication:

1. At the Windows 2000 desktop, click HAFM at the task bar (bottom of the

desktop) to maximize the Product View page.

2. At the Product View page, inspect the shape and color of the symbol behind the

Edge Switch 2/32 icon.

Table 2–2

explains operational states and associated

symbols.

3. Double-click the switch icon. The Hardware View page for the selected switch

displays, as shown in

Figure 2–8

. In the example, FRU failures are indicated by

Flashing red and yellow diamonds, and switch degradation is indicated by the
yellow triangle at the alert panel.

Table 2–2: Switch Operational States and Symbols

Operational State

Symbol

Operational—switch-to server communication is established, the
switch is operational, and no failures are indicated. Go to “

Task 11:

Set Switch Date and Time

” on page 2–21.

Degraded—switch-to server communication is established, but the
switch is operating in degraded mode and requires service. This
condition is typical if a port or redundant FRU fails. Go to

step 3

.

Failed—switch-to server communication is established, but the
switch failed and requires immediate service. Go to

step 3

.

Status Unknown—the switch status is unknown because of a
network communication failure between the switch and

HAFM

server. Go to

step 3

.