Task 16: cable fibre channel ports, Task 17: connect switch to a fabric (optional), Ed up, go to – HP 958-000290-000 User Manual

Page 95: Task 16: cable fibre channel, Ports

Advertising
background image

edge switch 2/32 installation guide

2-69

Installing and Configuring the Edge Switch 2/32

Task 16: Cable Fibre Channel Ports

Perform this task to connect devices to the switch. To cable Fibre Channel ports:

1. Route singlemode or multimode fiber-optic cables (depending on the type of SFP

pluggable optic transceivers installed) from customer-specified devices to ports at
the front of the switch.

2. Connect device cables to small form factor pluggable (SFP) transceivers. Start

with port 0 and continue sequentially to the left through port 31.

3. Perform one of the following:

a.

If the switch is installed on a table or desk top, bundle and secure the Fibre
Channel cables as directed by the customer.

b.

If the switch is installed in a customer-supplied equipment rack, bundle Fibre
Channel cables from the switch and other equipment (groups of 16
maximum), and secure them as directed by the customer.

4. Set the switch online.

Task 17: Connect Switch to a Fabric (Optional)

To provide Fibre Channel connectivity between public devices and fabric-attached
devices, connect the switch to an expansion port (E_Port) of an HP director or switch.
The switch port to switch port connection is called an interswitch link (ISL). To
fabric-attach the switch and create an ISL:

1. Ensure the switch is defined to the HAFM application (defined while performing

Task 6: Configure the Switch to the HAFM Application

” on page 2–13.

2. Ensure the preferred domain ID for the switch is unique and does not conflict with

the ID of another switch participating in the fabric. To change the domain ID, see

Task 12: Configure the Edge Switch 2/32 Product Manager Applications

” on

page 2–23.

3. Ensure the R_A_TOV and E_D_TOV values for the switch are identical to the

values for all switches participating in the fabric. To change the values, see

Task

12: Configure the Edge Switch 2/32 Product Manager Applications

” on

page 2–23.

4. Route a multimode or singlemode fiber-optic cable (depending on the type of SFP

transceiver installed) from a customer-specified E_Port of the switch to the
switch.

Advertising
This manual is related to the following products: