Readiness checklist, Table 20 readiness checklist – Nortel Networks NN43001-314 User Manual

Page 222

Advertising
background image

222

MG 1000B platform hardware installation

To connect to the PSTN, use one of the following interface cards:

1.5 Mb T1 Multi-functional Digital Interface

Extended Universal Trunk (analog)

2.0 Mb Digital Trunk Interface (DTI)

2.0 Mb Primary Rate Interface (PRI)

The MG 1000B Expander will support digital trunks if configured with a
media gateway controller.

Each MG 1000B Core with a digital trunk card must have a clock controller.
See Circuit Card Reference(NN43001-311).

The MG 1000B platform must have a Signaling Server that can be installed
in the same rack as the MG 1000B Core and MG 1000B Expander. The MG
1000B Expander is optional and follows the same installation procedure as
the MG 1000B Core.

Readiness checklist

Before starting the installation, use the checklist in

Table 20 "Readiness

checklist" (page 222)

to make sure you are ready.

Table 20
Readiness checklist

Have you:

ü

Read all safety instructions in Communication Server 1000E: Installation
and Configuration (NN43041-310)
?

Received all equipment?

Made sure the area meets all environmental requirements?

Checked for all power requirements?

Checked for correct grounding facilities?

Developed an equipment layout plan for the system?
This information is provided by your Planning and Engineering group.

Completed the card slot assignment plan?
This information is provided by your Planning and Engineering group.

Obtained all the tools required to continue with the installation?

Prepared the network data as suggested in Converging the Data Network
with VoIP Fundamentals (NN43001-260)
and Communication Server
1000E: Installation and Configuration (NN43041-310)
?

Nortel Communication Server 1000

Branch Office Installation and Commissioning

NN43001-314

01.02

Standard

Release 5.0

20 June 2007

Copyright © 2007, Nortel Networks

.