Table 21 tools checklist, Procedure 13, Inch rack – Nortel Networks NN43001-314 User Manual

Page 223

Advertising
background image

Installing an MG 1000B Core

223

Tools checklist

To install the system correctly, make sure that the tools listed in

Table

21 "Tools checklist" (page 223)

are available before assembling the

components.

Table 21
Tools checklist

Tools and components

ü

screwdrivers

an ECOS 1023 POW-R-MATE or similar type of test meter

appropriate cable terminating tools

a drill for making lead holes

a computer for connecting directly to the MG 1000B Core by a DTE—DTE
null modem cable, with:

teletype terminal (ANSI-W emulation, serial port, 19 200 bps) for the
Call Server, MG 1000B Core, Signaling Server, and Media Cards

a web browser for Element Manager and NRS Management
(configure cache settings to check for new pages every time and to
empty the cache when the browser is closed)

Rack-mounting an MG 1000B Core or MG 1000B Expander

Items required

To install each MG 1000B Core or MG 1000B Expander in a 19-inch rack,
use the following items:

equipment layout plan (discussed in Communication Server 1000E:
Installation and Configuration (NN43041-310)
)

one pair of left and right guide brackets

one pair of left and right ear brackets

eight #12-24 screws

four #8-32 machine screws

The NTTK09 kit contains all of the above items with the exception of the
equipment layout plan and screws.

Procedure 13

Mounting the MG 1000B Core or MG 1000B Expander in a 19-inch rack

Step

Action

References to "MG 1000B Core" in the following steps also apply to the
MG 1000B Expander.

Nortel Communication Server 1000

Branch Office Installation and Commissioning

NN43001-314

01.02

Standard

Release 5.0

20 June 2007

Copyright © 2007, Nortel Networks

.

Advertising