Verifying a successful configuration, Connecting the mg 1000b core to the network, Procedure 20 verifying successful configuration – Nortel Networks NN43001-314 User Manual

Page 244: Procedure 20, Verifying successful configuration

Advertising
background image

244

MG 1000B software installation

—End—

After installing software and configuring basic information about the
Signaling Server, the Signaling Server components can be configured using
the web-based Element Manager interface. See Element Manager System
Reference - Administration (NN43001-632)
.

Verifying a successful configuration

To ensure that ELAN and TLAN network interfaces on the Signaling Server
are configured correctly, perform a ping test at each interface.

Procedure 20

Verifying successful configuration

Step

Action

1

From the Call Server, in LD 117, enter:

ping <ip address>

2

From the Media Card, log in to the Media Card and enter:

ping "ip address",3

3

From the Signaling Server, log in and enter:

ping "ip address",3

—End—

Connecting the MG 1000B Core to the network

Connecting the MG 1000B Core to the network

The MG 1000B Core has two 10/100BaseT ports (1 and 2) and one
Attachment Unit Interface (AUI) port at the back on the lower left-hand side.
See

Figure 88 "Back of MG 1000B Core" (page 245)

.