Installation – Teledyne 6600 User Manual

Page 73

Advertising
background image

Oil in Water Analyzer

Part II: Analysis Unit

Part II: 2-1

Teledyne Analytical Instruments

Installation

Installation of the Model 6600 Photometric Analyzer includes:

1. Unpacking
2. Mounting
3. Fluid connections
4. Electrical connections
5. Testing the system.

2.1

Unpacking the Analyzer

The analyzer is shipped with all the materials you need to install and

prepare the system for operation. Carefully unpack the analyzer and inspect
it for damage. Immediately report any damage to the shipping agent.

2.2

Installing and Connecting the Analyzer

Without Temperature Control, the system must be installed in an area

where the ambient temperature is not permitted to drop below 32°F freezing nor
rise above 122°F (0-50°C).

Regardless of configuration, the system must be installed on a level surface

with sufficient space allocated on either side for personnel and test equipment
access. Subject to the foregoing, the system should be placed as close to the
sample point as possible and bolted to its supporting surface. A waterproof
mastic should be liberally applied to the under surfaces of all four supporting legs
of the cubicle system before placing it in position and bolting it in place.

2.2.1 User Connections

All user connections are around the periphery of the equipment

panel (or cubicle) and appear in the outline diagram in the back of the manual.