Programmed values – York YCAS0130 User Manual

Page 118

Advertising
background image

118

YORK INTERNATIONAL

FORM 201.19-NM1 (204)

5. Program the required op er at ing val ues into the

mi cro for cut-outs, safe ties, etc. and record them
in the chart be low. See Page 166 for details.

Record programmed values in the chart below.

PROGRAMMED VALUES

Display Language = _________________________

Discharge Press Cutout = ___________PSIG (kPa)

Discharge Press Unload = ___________PSIG (kPa)

Suction Press Cutout = _____________PSIG (kPa)

High Amb Cutout = ___________________ °F (°C)

Low Amb Cutout = ____________________ °F (°C)

Leaving Chilled Liquid Temp Cutout = _____ °F (°C)

High Motor Current Unload = ____________ % FLA

Anti-Recycle Time = ____________________Secs

Local / Remote Mode = ______________________

Display Units = _________________________

Lead / Lag Control = ________________________

Power Failure Restart = _____________________

Suction Superheat Setpoint = __________ °F (°C)

6. Program the Chilled Liquid Setpoint/Range and

record:

Setpoint = __________________ °F (°C)

Range =

+/-

________________ °F (°C)

Keep in mind that the setpoint temperature dis-

played by the micro should equal the de sired
leav ing wa ter tem per a ture.

7. Assure that the CLK jumper J18 on the Mi cro -

pro ces sor Board is in the ON position (Top 2
pins).

8. Set the Time and Date.
9. Program the Daily Schedule start and stop

times.

10.Check the Factory Service Mode programming

values, (See Section 8.9) assure they are correct,
and record the values below:

Refrigerant Type = __________________________

R407C Chiller Type = ________________________

Unit Type = _______________________________

16.Assure that the Flow Switch is properly in-

stalled, wired correctly, and working.

17. Assure bolts through compressor feet to bottom

frame rails are removed.

PANEL CHECKS

(Power ON – Both System Switches “OFF”)

1. Apply 3-phase power and verify its val ue (See

Fig. 9 and 10 pages 36 and 37).

2. Apply 115VAC and verify its value on the ter-

mi nal block in the lower left of the Power Pan el.
Make the mea sure ment between ter mi nals 5 and
2 (See Fig. 14, page 41). The voltage should be
115VAC +/- 10%.

3. Assure the heaters on each compressor are on.

Al low the compressor heaters to remain on a
min i mum of 24 hours before start- up. This is
im por tant to as sure that no re frig er ant is in
the com pres sor oil at start-up!

4. Program the dip switches on the mi cro pro ces sor

board for the desired operating re quire ments. See
Fig. 49, Page 147. OPEN = Left side of switch
pushed down. CLOSED = Right side of switch
pushed down.

SWITCH

SWITCH "OPEN"

SETTING

SWITCH "CLOSED"

SETTING

1

Water Cooling

Glycol Cooling

2

Standard Ambient

Control

Low Ambient Control

3

Refrigerant R-407C

Refrigerant R-22

4

Do Not Use

YCAS

5

Do Not Use

Motor Current

Averaging (Start-Up)

Disabled

6

Heat Recovery

Disabled

Do Not Use

7

Expansion Valve

Thermostatic

Expansion Valve

Electronic*

8

Standard Options

Enabled

Do Not Use

*Expansion valve electronic should always be selected when an
EEV is installed.

Verify the selections by pressing the OP TIONS Key on
the control panel. Check them off in the chart above.

Damage to the chiller could result
if switch es are im prop er ly pro-
grammed.

Technical Data