Attaching the a-frame to the eave bracket, Chapter 7: roof assembly – Grain Systems Tanks PNEG-4075 User Manual

Page 102

Advertising
background image

Chapter 7: Roof Assembly

Figure 7-25 Exploded view of A-frame to center collar

A

A-frame rafter assembly

C

1/2 x 1-3/4 in. flange bolt (S-10252)

B

Center collar (CTR-0217 and CTR-0233)

D

1/2 in. flange nut (S-10253)

Attaching the A-Frame to the Eave Bracket

Assemble the lower portion of the A-frame rafters to the sidewalls.

1. Lower the A-frame rafter assembly (A) along the side of the eave bracket (C), and align with the

proper holes.

NOTE: Use the alignment hole (E) in the rafter to help align the holes with a punch tool.

2. Install flange bolts (B) and flange nuts (D), securing one side on the A-frame assembly.

3. Repeat this procedure for the other side of the A-frame.

4. Tighten to the recommended torque specifications. See

Bolt Torque Specifications, page 24

.

102

Pneg-4075 75 Ft Diameter 40-Series Bin

Advertising