Assembling the roof panel clips, Chapter 7: roof assembly – Grain Systems Tanks PNEG-4075 User Manual

Page 103

Advertising
background image

Chapter 7: Roof Assembly

Figure 7-26 Attaching the rafter to the eave bracket

A

A-frame rafter assembly

D

1/2 in. flange nut (S-10253)

B

1/2 x 1-3/4 in. flange bolt (S-10252)

E

Hole for alignment tool

C

Eave bracket (CTR-0429)

After You Finish
Continue to the next A-frame installation until all of the A-frame rafter assemblies are installed. See

About

Temperature Cable Brackets and A-Frame Assemblies, page 75

.

Assembling the Roof Panel Clips

The roof panel clips are located at the top of the roof rafters nearest to the center collar rafter clips.

Before You Begin

The A-frame rafters should be fully assembled and installed to the center collar and the eave brackets.

What You Should Know

The A-frame assembly consists of two roof rafters identified as the left-hand roof rafter (A) and the right-
hand roof rafter (C). The roof panel clip is installed between each rafter after the A-frame assemblies are
installed.

1. Attach the two roof panel clips (B) to the left-hand roof rafter (A), and install two flange bolts (D) and

two flange nuts (E) securing the roof panel clips to the left-hand roof rafter.

2. Attach the third roof panel clip (B) to the right-hand roof rafter (A), and install two flange bolts (D) and

two flange nuts (E) securing the roof panel clips to the right-hand roof rafter.

Pneg-4075 75 Ft Diameter 40-Series Bin

103

Advertising