Grain Systems Tanks PNEG-4075 User Manual

Page 117

Advertising
background image

Chapter 7: Roof Assembly

6. Locate two long center collar channels (I), and place on stands or suitable blocks.

NOTE: Make note of the orientation of each center collar channel prior to assembling. Ensure all cap

plate holes are facing in the same direction.

7. Locate the two short center collar channels (F) that were previously assembled, and place between

the two long center collar channel (I).

8. Install the short center collar channels (F) to the third set of holes located on each long center collar

channel (I).

9. Install flange bolts (G) and flange nuts (H), securing the short center collar channel (F) to the long

center collar channel (I).

10.Repeat this procedure for the second short center collar channel (F).

11.Tighten all of the hardware to the recommended torque specifications. See

Bolt Torque Specifica-

tions, page 24

.

Pneg-4075 75 Ft Diameter 40-Series Bin

117

Advertising