Cut to Length with Multi Stroke Program

Once the servo/cutter combination is in place and the cables have been
attached, you can proceed with testing the unit. The first step is to turn on the
main disconnect switch on the electrical enclosure. Next, at the operator’s
console, pull the power on-off button to the on position. The button should
illuminate to indicate that there is power to the system.

The Pacific Scientific drive performs an initiate sequence to check it’s internal
program. At this time the display should show the Rapid-Air screen for 5
seconds before starting the main setup program. If you are comfortable with
programming a job then continue, it not, please refer to the “Programming
Procedure” located in this manual.

Follow the programming sequence for the operators terminal to input
parameters into job storage. Your servo feed has been fully tested before it
was shipped to your facility and this procedure is merely a test to insure that
all functions are still functional and the cables are properly seated.

Once you have programmed the required parameters, select the manual
mode of operation. If the option of air regulated upper feed roll was
purchased, check that the main air is at least 80psi and check that the roll
pressure gage is functional by adjusting the pressure up and down. This is
accomplished by turning the pressure adjust knob. If you did not purchase the
air regulated roll option then check that you have enough tension on the
material to avoid slipping during feeding. Open and close the feed and anti-
backup rolls electrically or manually. Visually inspect that the rolls open and
close as you press the appropriate keys on the keypad or when using the
manual levers.