3 Installation

894 Professional CVS

■■■■■■■■

37

Connecting an FEP tubing to the waste canister

A 5-way tubing connector (6.1828.020) is required to connect FEP tubings
to a waste canister. Figure 43, page 69, provides an overview of the
tubing setup between the waste canister, 843 Pump Station and 894 Pro-
fessional CVS.

1

2

Figure 28

Connecting the 5-way tubing connector to a waste canister

Proceed as follows:

1 Unscrew the cap with the hole in the center from the waste canister.

2 Feed each of the five tubings from the 5-way tubing connector with

the couplings already installed from below through the hole of the
unscrewed cap.

3 Screw the cap with the 5-way tubing connector inserted back onto

the waste canister.

4 Screw the tubing nipples of the FEP tubings (e.g. 6.1805.530) to the

couplings of the tubings.

NOTE

In order to ensure that liquid is transported smoothly from and to the
canisters, the canisters must not be air-tight. If necessary, loosen the
screw cap a little.

Connecting an FEP tubing to a dosing unit with VMS

Proceed as follows: