Please read all installation instructions carefully before
proceeding. Wiring diagrams are located in the
appendix of this manual. Use the BTU Meter Certificate
of Calibration (C of C) to verify that the Specified
Installation & Operating Parameters match the actual
conditions at the location where the meter is installed.
A worksheet for checking off these steps and recording
measured values is located on the following page.

4.7 COMMISSIONING

Upon initial installation, it is strongly recommended that both the System-10 and its associated flow
meter be commissioned to ensure that they are properly installed and functioning correctly. This
process involves verifying the mechanical installation, measuring flow and temperature signals and
then comparing these measurements to the specified installation and operating parameters listed on the
certificate of calibration provided with the meter. The data collected during this initial commissioning
process will then serve as baseline data for periodic revalidation of the meter operation.

COMMISSIONING PROCEDURE - ONICON BTU METERS