INSTALLING OPTIONAL ACCESSORIES

EATON Powerware

®

9315 UPS (500–750 kVA) Installation and Operation Manual

S 164201691 Rev 1 www.powerware.com

6-4

6.

Connect the RMP wiring to the terminal block using terminations shown in
Table 6-2.

Table 6-2. RMP Wire Terminations

From RMP A

To UPS

Remarks

TB1-4

TB3-1

TB1-5

TB3-2

Twisted wires (4)

TB1-6

TB3-3

Twisted wires (4)

1–2 turns per 3”

TB1-7

TB3-4

From RMP B (If Used)

To UPS

Remarks

TB1-4

TB3-5

TB1-5

TB3-6

Twisted wires (4)

TB1-6

TB3-7

Twisted wires (4)

1–2 turns per 3”

TB1-7

TB3-8

7.

To check the RMP operation, ensure that the UPS system is supplying the load
via the inverter or bypass. If the RMP indicators show the appropriate status,
then it is operating correctly.

If the communication link between the UPS and the RMP is not present, the
RMP conducts a self-test (all indicators flash and the horn beeps at one-second
intervals); check all harness connectors and the fuse for proper seating. If all
connections are secure but the RMP continues to self-test, replace the fuse with
the spare included in the hardware kit. If this does not correct the problem,
contact your Eaton service representative for verification that the RMP is working
correctly.

8.

To test the light emitting diode (LED) lamps behind the indicators, press and hold
the horn silence button for three seconds. All the indicators illuminate and the
horn sounds continuously until you release the button. If any indicator does not
illuminate, its LED lamp may need to be replaced. Contact your Eaton service
representative if you have a problem with the LEDs.

9.

Repeat Steps 1 through 8 if you are installing another RMP.

10. If you are installing an RIM or SCM in addition to an RMP, proceed to

paragraph 6.2 or 6.3, respectively; otherwise, secure the access plate on top of
the UPS Input/Rectifier cabinet.