9315 UPS (500–750 kVA) Installation and Operation Manual

S 164201691 Rev 1 www.powerware.com

12-12

12.5.7

Battery Test Setup

If Battery Test Setup (option 5) is selected from the Main menu (see page 12-9), the
following menu is displayed:

NOTE If a message stating “Battery Test Requires Calibration” appears, please notify your Eaton service
representative for proper calibration.

Battery Test Setup
1. Setup One-time Delayed Battery Test
2. Setup Monthly Battery Test
3. Setup Quarterly Battery Test
4. Cancel Pending Battery Test
5. Display Next Scheduled Battery Test
6. Return to Main Menu
Enter Selection:

This menu allows you to schedule battery tests, review scheduled battery tests, or
cancel pending battery tests. If you select 1, 2, or 3 from this menu, the following
menu is displayed:

Enter Starting Month (1–12):
Enter Day of Week, Sunday = 1, (1–7):
Enter Week of Month (1–5):
Enter Hour of Test (0–23):
Enter Minute of Test (0–59):
<CR> with no entry will return to Battery Test Setup Menu.

NOTE Follow each entry with a carriage return <CR>.

Enter the information at the prompt with a carriage return to schedule the battery
test.

If 4 is selected from the Battery Test Setup menu, you are prompted to enter Y to
cancel all pending tests. This selection will only cancel pending tests and will not stop
a test currently in progress.

If 5 is selected from the Battery Test Setup menu when a Battery Test is scheduled,
the following is displayed:

Next Battery Test Scheduled
WK DAY MON HR:MN
4

FRI MAR 15:34

Enter <CR> to return to Battery Test Setup Menu

If 5 is selected from the Battery Test Setup menu when a Battery Test is not
scheduled, the following is displayed:

No Battery Test Scheduled
Enter <CR> to return to Battery Test Setup Menu

NOTE The unit will only perform one battery test in any 24 hour period.