Grain Systems PNEG-365 User Manual

Page 30

Advertising
background image

Grain Systems, Inc. Assumption, Ill.

30

18' Manual Batch

DUMP CHUTE CHAIN ASSEMBLY

Attach all 18 dump chute chains directly to the lift plate as shown in diagram below.

Install all chains using "S" hooks (S-4692) to attach the chains to the dump chutes and lift plates. Keep excess chain

at the lift plate. Adjust the chains until the chutes are approximately level when the lift plate is in the closed (up)

position. Once the chains are uniformly adjusted, crimp the "S" hooks closed. Check when attaching the "s" hook to

the end link on a chain that the end has not been cut open. If this is found remove the end link or shift up and use the

next link in chain. The lift plate should be approximately 12" down from the cross channel when the chutes are level.

REV. 9-30-96

Figure #34

Chain leading to outer chutes

(82") Adjust length as required

TD-100205

Cable Clamp

S-4693

Loop in Cable

Chutes in closed position

Center Lift Plate

(TD-100801)

Crimp "S" hooks after

final chute adjustment

Center Collar

Cross Brace

Lift Plate

To sidewall pulley

assembly

12" when chutes are level(closed)