3.0 Installation,

continued

3.2 Installation, CE-3x2 5K-T

Prior to installation verify the following:

All necessary grounding rods and materials are in place.

Utility power was run to site in accordance with the NESC (National Electric Safety
Code).

Obtained local safety practices for working with high-voltage systems.

Gas piping, hardware, supports, and other gas carrying components to the pad location
conform to NFPA standard and local requirements.

Required Tools and Materials:

Crane to lift enclosure from shipping pallet and place on pad

Key(s) to enclosure doors

• Digital

voltmeter

Torque wrench with insulated handle and 7/16" socket

7/16” box-end wrench

NO-OX or other suitable corrosion inhibiting agent (NCP-2)

Silicone sealant GE RTV123 (or equivalent)

Phillips screwdriver (for pad shear mounting)

5/8" socket for removing pallet mounting bolts

• Hard

hats

• Utility

knife

To prevent injury or death, do not walk, or allow personnel to walk, beneath the suspended
unit. Use steel-toe work shoe protection. Use hard hats at all times during this procedure.
Before lifting, verify the transport path is clear of obstructions.

WARNING!