5.3

Putting the appliance into operation

5.3.1.

Commissioning

CAUTION

Initial commissioning must be done by a qualified

professional.

Carry out the commissioning operations in the following order:
1. Connect to the mains.
2. Check that no error codes or messages are shown on the display.

The domestic hot water set point temperature is set to 55°C in

comfort mode.

3. Select the Boost operating mode.

¼See chapter: "Choosing the operating mode", page 46

4. The compressor starts up after 120 seconds if DHW production is

required.

5.4

Checks and adjustments after commissioning

4

Check the leak tightness of the connections.

4

Check the temperature of the 3 DHW temperature sensors to

ensure that the appliance operates correctly.

If the readout values are incorrect, check the positioning of the

sensors in the sensor tube.

4

A few days after start up of the appliance, a visual inspection must

be made to check for any leaks in the water system or any

blockages in the condensates runoff.

5.5

Choosing the operating mode

The operating mode is shown on the main display.
1. To change the operating mode, press the MODE key several times

until the symbol corresponding to the desired operating mode

appears on the display.

C003493-A

1

4

3

4

1

2

5. Commissioning

TWH 200E TWH 300E TWH 300EH

46

03/02/2014 - 300026515-001-03

Advertising