The gas supply and the electrical supply are to be provided by the customer prior to instal-

lation. The picture shows a typical utility rough-in for a triple stack oven. Preparing the utilities
this way allows for an easy third deck addition if a double stack oven is initially installed.

All installations must conform to local building and mechanical codes. It is required that

the ovens be placed under a ventilation hood. The gas supply should have a gas meter and regula-
tor large enough to handle all of the gas appliances, such as the furnace, hot water heater, and ov-
ens, in operation at the same time. Add up all of the BTU / kw / MJ ratings to determine the total
load. (See Oven Specifications page for supply requirements).

Oven Only Rough-In Specifications

1. All dimensions in inches [mm].
2. All dimensions on this page are recommended.

42.00

[1067]

48.00

[1219]

6.00

[152]

3.00

[76]

Electrical Supply

Gas Manifold

6.00 [152]

From back of oven to wall

Utilities must be easily accessible when the ovens are in the installed position. Do not install utilities