Hood installation hang hood from ceiling joists – XLT XD-9010B User Manual

Page 76

Advertising
background image


76

Hood Installation

Hang Hood From Ceiling Joists

After the AVI Hood has been installed on top of the ovens and moved into position, it must

be hung from the building structure to relieve the weight from the ovens and to allow the ovens to
be moved for maintenance and cleaning. XLT Ovens supplies two (2), 24” [610mm] long pieces
of Unistrut for installation under the horizontal air duct located in the center of the hood. Shown
below is a typical installation using four (4) pieces of Unistrut and four (4) lengths of 1/2”-13 all-
thread. It is recommended that a flat washer and two (2) nuts be placed under the bottom piece of
Unistrut and over the top piece to prevent the hood from moving after installation is complete.
Please note the final distance from the finished floor to the bottom of the hood must be 69 1/2” +/-
1/8” [1765mm +/-3.2], measured at all four (4) corners.

Unistrut

Flat Washer
1/2-13 Nuts (2)

1/2-13 All-thread (4 places)

Welded Duct

Ceiling Joist (shown
for reference only)

Finished Floor

69 1/2

±1/8

[1765

±3.2

]

Front fascia panel removed for clarity

Horizontal Duct

Advertising