Changing the hardware communications protocol, Installing scaling resistors, Figure 6.5—jumper configurations 157 – Watlow CPC400 User Manual

Page 171

Advertising
background image

CPC400 Series User’s Guide

Chapter 6: Troubleshooting and Reconfiguring

Doc. 0600-2900-2000

Watlow Anafaze

157

Changing the Hardware Communications Protocol

To switch between EIA/TIA-232 and EIA/TIA-485, change
the jumpers as shown in Figure 6.5.

Figure 6.5

Jumper Configurations

You will need tweezers and a Phillips head screwdriver to
switch between EIA/TIA-232 and EIA/TIA-485:

1.

Power down the unit.

2.

Remove the controller’s metal casing. See Replacing
the Flash Memory Chip on page 154
for step-by-step
instructions.

3.

Find jumpers JU2, JU3, JU4, and JU5 on the board.

4.

Use tweezers to carefully grasp the jumpers and gen-
tly slide them off the pins.

5.

Use tweezers to gently slide jumpers JU2, JU3, JU4
and JU5 onto the correct pins (see Figure 6.5).

6.

If you are configuring the controller as the last device
on an EIA/TIA-485 network, move JU1 to the B posi-
tion.

7.

Reassemble the controller.

Installing Scaling Resistors

Resistors are installed for all inputs on the CPC400. Inputs
with signal ranges between -10 and +60 mV use 0

resis-

tors in the RC position only. All other input signals require
special input scaling resistors.

JU1
JU2
JU3
JU4
JU5

A

B

A

B

A

B

Configured for

EIA/TIA-232

Configured for

EIA/TIA-485

Last controller in

system configured

for EIA/TIA-485