Install In-Line Pump and Assemble Supply
Line

1. Place In-Line Pump on the platform as shown above. Install the Strainer Basket O-

rings. Connect the lower port of the strainer basket to the In-Line Pump inlet using the
liquid-tight fitting attached to the strainer basket. Hand-tighten ONLY.

2. Connect the upper port of the strainer basket to the union. Hand-tighten ONLY.
3. Connect two 1-1/2" (3.8 cm) couplings; One to the outlet side and another to the inlet

side of the filter. Cut two 4" (10.16 cm) lengths of 1-1/2" (3.8 cm) dia. PVC pipe.
Install one end of pipe to strainer basket union and the other end to the 1-1/2" (3.8cm)
coupling on the outlet-side of the filter.

NOTE: Install filter with the arrow pointed in the direction of water flow (toward the In-

Line Pump).

4. Connect the other 4"(10.16cm) length piece of pipe to the inlet-side of the filter and to

the ball valve.































5. Measurements will need to be verified before installation

of the remaining section of pipe from the ball valve to the
1-1/2" (3.8 cm) coupling at the 8" end-cap.

6. Use two 1-1/2" (3.8 cm) elbows to install remaining

sections of PVC pipe from the ball valve to the end-cap
coupling. Cut PVC pipe as required. See the In-Line
Pump supply line diagram.

Pump

90 degree Elbows

1-1/2" (3.8 cm)

Coupling

Filter

Strainer

Basket

Union

(Supplied with pump)

1-1/2"(3.8 cm)

Coupling

Float Valve