3 ia-ring – Atop Technology EH7510 User manual User Manual

Page 78

Advertising
background image

Atop Industrial Managed Ethernet Switch
EH7510
User Manual V 1.0

72

5. On EH7510 A, Click

“Configure” on RAPS VLAN and setup as the below figure.

Fig. 2.61

6.

Open EH7510 B’s WebUI and setup ERPS settings like the following.

Fig.2.62

7.

Connect EH7510 A’s Port 7 to EH7510 B’s Port 8. Connect EH7510 A’s Port 8 to

EH7510 B’s Port 7 (like cross-over) for the redundancy port.

8. If everything is setup properly, you will find EH7510 A to have the following ERPS state.

It will automatically block Port 8 to prevent network loop.

Fig. 2.63

9. Now you can add any other bridge that you want in between the two EH7510s.