Installation and mechanical alignment, 2 controller mounting, 3 emitter and receiver hookups – Banner A-GAGE MINI-ARRAY Series User Manual

Page 14

Advertising
background image

14

P/N 43298 rev. E

Banner Engineering Corp.

Minneapolis, MN U.S.A.

www.bannerengineering.com • Tel: 763.544.3164

MINI-ARRAY

®

Instruction Manual

Installation and Mechanical Alignment

Figure 3-2. MINI-ARRAY emitter and receiver mounting bracket dimensions

Mount the emitter and receiver in their mounting brackets (shown in Figure 3-1),

and position the red lenses of the two units directly facing each other. The connector

ends of both sensors must point in the same direction. Measure from one or more

reference planes (i.e., the floor) to the same points on the emitter and receiver to

verify their mechanical alignment. If the sensors are positioned exactly vertical or

exactly horizontal, a carpenter’s level may be useful for checking alignment. Extending

a straight-edge or a string between the sensors may help with positioning. Also check

by eye for line-of-sight alignment. Make any necessary final mechanical adjustments,

and hand-tighten the bracket hardware. See Section 5 for information on alignment

indicators and the use of the alignment software supplied with the controller.

Connect the shielded cables to the emitter and receiver, and route them to the

controller location. Follow the local wiring code for low-voltage dc control cables. The

same cable type is used for both emitter and receiver (two cables required per system).

Cut the cables to length after making sure they are routed properly. Remove cable braid

at the controller connection points (see Figure 3-4).

3.2 Controller Mounting

The controller must be installed inside an enclosure with a NEMA (or IEC) rating

suitable for the operating environment.
Mounting dimensions for the controller are shown in Figure 2-2. The controller is

supplied with M3.5 x 0.6 hardware for direct mounting to a surface, or it can be

mounted onto standard 35 mm DIN rail.

3.3 Emitter and Receiver Hookups

Emitter and receiver cables connect in parallel to controller terminals #4 through #8.

Connect the wires from both sensor cables, as follows:

Terminal 4

Brown

Terminal 5

Blue

Terminal 6

Bare

Terminal 7

Black

Terminal 8

White

Trim off the foil shield and the braided shield at the point where the wires exit the cable

(see Figure 3-4).

The “drain wire” is the uninsulated stranded

wire which runs between the braided shield

and the foil shield. Remove the foil shield

and braided shield at the point where the

wires exit the cable.

Figure 3-4. Emitter/receiver cable

preparation

Trim braided shield flush

with cable

Trim foil shield flush

with cable

Uninsulated

drain wire

Emitter or

Receiver

8.1 mm

(0.32") max.

0.5" (13 mm) radius minimum bend

71 mm

2.8"

Figure 3-3. Quick-disconnect cable

clearances

Advertising