The second to last row, front, 
middle brick must be the last 
brick installed. A shim may be 
used to hold the upper brick in 
place, or it is more easily 
accomplished by leaving the 
middle brick in the second to 
last row pulled about 4" 
forward from its intended 
position. In this position the 
brick will act as a support for the top middle brick. Push the front, middle brick in the second to 
last row into place which will at the same time push the middle brick that was left forward into 
place.  (See Figure 7 for a picture depiction of this procedure.) 

INSTALLING THE HEATING ELEMENTS 

Step  1 

After all bricks are loaded, insert the heating elements (17) between the brick layers with the cold 
pins facing up. (See picture depictition of element termination in Figure 6 for reference to cold pin 
direction.) 

Step  2 

Make the heating elements (17) to wiring harness (19 & 65) connections. (See Figure 6 for a picture 
depictition of element termination.) 

Use  two  3/8"  wrenches  to  ensure  tight  connections  and  to  avoid  twisting  the 
threaded  element  cold  pins  off. 

Step  3 

Replace the front aluminized steel panel (10). 

This  panel  MUST  be  installed  with  its  air  deflectors  (arrow  shaped  pieces)  facing 
inward  and  with  the  narrow  ends  of  the  deflectors  pointing  up. 

Step  4 

Lower the insulation blankets (3, 4, & 5) back into position, one at a time. Carefully tuck the sides of 
this insulation into the edges, corners, and around the exposed portions of heating elements (17). 

Step  5 

Replace the galvanized front panel utilizing the original #8 x 1" sheet metal screws that were re­ 
moved. 

Step  6 

Replace the painted front panel (11) using blunt tip screws only. 

DUCTING 

Air Flow 

The Steffes furnace has been specially designed for versatility and may be installed to meet right­to­left or left­ 
to­right air flow requirements.  The furnace is factory configured for a left­to­right air flow.  If it is desired to 
reverse the air flow, do the following: 

Step  1  Reroute the supply air blower wiring harness (55) to the opposite side of furnace base by fishing the 

harness between bottom radiant heat shield (51) and bottom panel (47). Be sure to route the wiring 
harness away from the  heat exchanger and place any excess wiring between  the radiant heat shield 
(51) and bottom panel (47). 

7

Installing The Furnace

(cont'd)

13

6

NOTE

NOTE 

FIGURE  7 

LAST (TOP) ROW 

SECOND TO LAST ROW 

MIDDLE BRICK