12 csd-1 manifold assembly (supplied), Modulex ext – AERCO Modulex EXT 1530 - 3060 User Manual

Page 30

Advertising
background image

MODULEX EXT

1530, 1912, 2295, 2677, 3060 Boilers

Installation, Operation & Maintenance Manual

3.12 CSD-1 MANIFOLD ASSEMBLY (SUPPLIED)

The installation of a flow switch, pressure/temperature gauge, and an ASME compliant safety

pressure relief valve designed for the boiler output capacity are required. These major

components are supplied with the boiler and must be assembled and wired when installing the

boiler at the site. The manifold assembly components supplied are:

3/4” Pressure Relief Valve

Flow Switch

Pressure/Temperature Gauge

The pressure relief valve and all other manifold components are shown in Figure 3-6.

Figure 3-6: Manifold Assembly and Components

To install the pressure relief valve and the other components shown, proceed as shown in

Instruction 4.0, below.

NOTE

Use Teflon tape or a suitable pipe joint compound for component

and piping connections described in the following steps. Refer to

Figure 3- 6 for component identification.

Installing the Pressure Relief Valve and Other Components

1. Attach manifold to the outlet supply connection on the boiler via the flanged connections.
2. Cut the flow switch paddle. For EXT models 1530 to 3060, cut for 4” pipe as directed in

the flow switch paddle packaging. For installations expecting less than a 10 gpm flow,

the switch must be adjusted as follows:
a) With no flow, turn adjustment screw on the switch counter-clockwise until the switch

trips.

b) Then turn screw 1/2 turn clock-wise and continue installation.

Flow Switch

3/4” Pressure Relief

Valve

Pressure/Temperature

Gauge

Page 30 of 138

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0095_0E