I.C.E. HTDM Food Process Unit User Manual

Page 8

Advertising
background image

8

COOLING


When installed downstream from a refrigeration system.

Condensation will form and provisions shall be made to dispose
of condensate.


HIGH ALTITUDE


As per June I, 1998 all HTDM units are derated four percent of
maximum input of each 1OOOft(305m) elevation above sea level.

INDOOR UNITS


Install an indoor unit in such that the gas ignition control
system is not directly exposed to water spray, rain or dripping
water.

GENERAL OPERATING INSTRUCTION

a) Refer to the rating plate for fuel input and supply

pressures.

b) Do not attempt to start the burner if the unit is full of

vapour gas, or if the combustion chamber is very hot.

c) Do not leave combustible material near the unit.
d) Shut off the manual fuel supply valve if the burner has been

shut down for an extended period of time.

e) Ensure clean-out doors are in place before starting the

burner.

f) Do not start the burner unless the blower access doors are

securely in place.

g) Refer to literature regarding controls, gas valves and other

components.

START-UP PROCEDURES


1. PRECAUTIONS

a) Ensure the main disconnect switch is in the “off”

position.

b) Ensure the burner on-off switch is in the “off” position.
c) Check all electrical and gas connections and tighten if

necessary

d) Check main fans (by rotating fan shaft by hand), bearing

set screws, and pulley set screws. Ensure blowers are free

to turn, vibration isolation shipping blocks are removed
(if equipped), shipped loose items (if supplied), are
removed from inside blower sections.

Advertising