12847

10 Standard Flue - Length, Preparation and Installation

13297

Diagram 10.17

Diagram 10.18

Push the flue assembly into the wall, externally or internally,

initially until the end of the assembly protrudes a short way

from the inside face of the wall. This will enable the internal

trim ring (if required) to be positioned and allow the flue

assembly to be drawn back into the flue elbow.
Secure the flue elbow in position on top of the boiler with four

torque headed screws supplied.
Draw the flue assembly from wall and engage the flue duct

into the elbow and butt fit between the air duct and flue elbow.

Fit the securing collar into position.

Ensuring correct alignment of the flue, mark through two of

the pre drilled holes in the securing collar. Remove securing

collar and drill two 3mm diameter holes one in the elbow and

one in the air duct, take care not to pierce the inner flue duct.

Fit the securing collar and secure with screws provided, see

diagram 10.18.
Slide the internal trim ring back against the wall, securing in

place with a small amount of sealant if required.
NOTE: If the air and flue ducts have been correctly cut to the

instructions the sealing collar should fit flush with the outside

wall.