12 commissioning – Glow-worm Ultrapower sxi Range User Manual

Page 40

Advertising
background image

40

12 Commissioning

IMPORTANT: At the time of commissioning, complete all

relevant sections of the Benchmark Checklist located in the

centre pages of this document.

12.1 Preliminaries - All Systems

Do Not operate the boiler without water.
The commissioning should be carried out by a

competent

person approved at the time by the Health and Safety

Executive in accordance with the current issue of BS6798.
Make sure that the system has been thoroughly flushed out with

cold water and that all cleanser if used has been removed.
Isolate the boiler from the mains electrical supply and test for

gas soundness and purge air from the gas supply.

12.2 Filling Domestic Water Circuit

Make sure that the isolation valves are securely tightened. Open

all domestic hot water taps.
Fully open the DHW outlet and DCW inlet valves, see diagram

12.1. Water will now flow through the boiler to the domestic

water tank and to the hot water taps.
Starting at the lowest tap, turn the hot taps off one at a time until

the hot water pipework is purged of air.
Carefully slacken, but DO NOT remove the air vent screw on

the domestic pump to release any trapped air within the boiler,

see diagram 12.2, secure when procedure completed.

NOTE:

The water pressure at the vent point is that of the

incoming water main (max 3.5bar due to pressure reducing

valve).
Check for water soundness of the complete domestic water

system.

Diagram 12.1

13445

12.3 Filling the Heating System

Refer to diagrams 12.1, 12.2 and 12.3.

With the boiler in place:
1. Ensure that the filling loop flexible hose is securely

connected to the double check inlet valve.
2. Ensure that the gas service isolation valve is closed.
3. Switch on the power supply to the appliance.

The boiler should be in OFF mode. This is indicated

by the ‘OFF’ symbol on the user interface display. If not,

press the ‘mode’ button repeatedly until the ‘OFF’ symbol

is displayed.

The display will now show a flashing system pressure.

13406

DOMESTIC

PUMP

DOMESTIC

PUMP VENT

Diagram 12.2