PDR 100 Fibre Channel Installation

50

PDR 100 Fibre Channel Installation

Installing the Fibre Channel Upgrade

Figure 14 identifies the board slot IDs and Figure 15 shows the locations and slot
IDs for the Slave EDR, Master EDR, and Fibre Channel boards. Installing the
Fibre Channel upgrade consists of the tasks listed below.

• Installing the 10/100 BaseT board, the Slave and Master EDR boards, and

the Fibre Channel board.

• Reinstalling board hold-down brackets.

• Reconnecting internal cables.

• Installing the PCI Interconnect board.

• Installing EMI compliance components, if necessary.

• Replacing the Profile covers.

• Replacing the Profile chassis into the rack.

• Connecting/reconnecting external cables and power cord.

NOTE: After board relocations, the slot ID stickers on the bottom rear panel
will no longer be valid. If you need new ID stickers, contact your Grass Valley
Group representative.