6.4 Commissioning the Sunny Beam

The first steps are described in detail, so that you can familiarize yourself with the controls of Sunny
Beam. Sunny Beam will guide you through the commissioning procedure. If a fault occurs during
commissioning, you can restart commissioning by pressing the push button for about 10 seconds, until
the SMA logo is displayed.

1. Insert the included batteries into the battery compartment of the Sunny Beam according to the

indication.

2. Press the button.

☑ The start screen appears.

3. Press the button.