Grid-tie inverter, Acld-40 controller – Magnum Energy AC Load Diversion Controller (ACLD-40) User Manual

Page 10

Advertising
background image

Page 3

©

2015 Sensata Technologies

Introduction

During a utility power outage (see Figure 1-2): When the utility power fails, the grid-tie inverter

disconnects (preventing the use of the renewable energy) and the MS-PAE Series inverter

automatically starts powering the critical loads. However, because the output of the MS-PAE

Series inverter is connected to the same AC bus as the grid-tie inverter and its output waveform

is compatible to the utility’s waveform, the grid-tie inverter re-synchronizes to the AC output

waveform of the MS-PAE Series inverter. After a minimum 5-minute disconnect period, the grid-

tie inverter reconnects and starts inverting all the energy from the renewable energy source just

like it did when it was connected to utility power.
The grid-tie inverter—now reconnected using the AC output waveform of the MS-PAE Series

inverter—converts as much of the available renewable energy as possible. However, during a

utility power interruption, the main panel loads are no longer connected and the utility grid is not

available to export any excess power that is generated. This means there may be more power on

the AC bus than the critical loads can consume, causing current to be pushed back thru the AC

output of the MS-PAE Series inverter into the battery bank. Since this is not the normal path for

the MS-PAE Series inverter to sense incoming current, it is not able to control the battery voltage

(or regulate the current, which requires the inverter to be rated to handle the full power output

of the renewable energy source). If the renewable energy provides more current that the critical

loads can use, there is the possibility that the battery voltage will rise and cause damage to the

battery. If the battery voltage is allowed to rise high enough, a High Battery Voltage fault on

the MS-PAE Series inverter will occur, causing it to turn off; which in turn shuts down the entire

system (i.e., critical loads and grid-tie inverter turn off). To prevent this from happening, there

must be a method of regulating the battery bank and ensuring it is properly charged; this is why

the ACLD-40 is needed.

Figure 1-2, ACLD Active (Utility Power NOT Available)

Battery Back-up Section

AC Load

(Primary)

ACLD Section

Main

Panel

Utility

Grid

Inverter

Battery

Bank

Grid-Tie
Inverter

Critical

Loads

Sub-

Panel

ACLD-40

Controller

Renewable

Energy

Power Flow

Renewable

Energy (RE)

Inverter power

(when RE not

available)

AC Load

(Secondary)

Advertising