Magnum Energy AC Load Diversion Controller (ACLD-40) User Manual

Page 21

Advertising
background image

©

2015 Sensata Technologies

Page 14

Installation

2.4.4

Wire Size and Overcurrent Protection

The wiring must be approved for the application (i.e., residential wiring) and sized per the local

electrical safety code requirements to ensure the wire’s ability to safely handle the maximum load

current. The wiring must be protected from short circuits and overloads by an overcurrent protection

device. This overcurrent protection device must have a means to disconnect the circuits (e.g., circuit

breaker or a fuse/disconnect), be properly sized, and branch circuit rated for the wire it is protecting.
As shown in Figure 2-5, the ACLD provides two input circuits, the Battery Based Inverter (BBI)

and Grid-Tie Inverter (GTI) input circuits. As part of the installation, overcurrent protection rated

to handle a maximum 30 amps must be provided from the source to these two input circuits. A

dual-pole, 30 amp, 240-volt branch rated circuit breaker to protect both L1 and L2 circuits for

each input circuit is required. Referring to Figure 2-6, the BBI input to the ACLD (terminals 1 and

2) is protected from a 30A breaker from the main utility panel; and the GTI input to the ACLD

(terminals 5 and 6) is protected using the 30A breaker in the MMP. Note: If the MMP enclosure is

not used, an external panel with a 30A breaker must be provided to protect the GTI input from

the Grid-Tie Inverter.
The ACLD also provides a primary output circuit (terminals 7 and 8) and secondary output circuit

(terminals 9 and 10) that are connected to the diversion loads. An external overcurrent protection

device is not required for these two output circuits as the diversion loads are the only connections

to these two circuits and these circuits are protected by the ACLD’s internal electronic overcurrent

protection circuitry.

CAUTION: The ACLD internal wires are rated for 30 amps, the pass-thru current must

be no greater than 30 amps or damage to the ACLD will occur.

CAUTION: The wiring must be no less than #10 AWG (5.3 mm

2

) gauge copper wire

and be approved for the application (i.e., residential wiring).

2.5 Torque

Requirements

Follow the specifi c torque recommendations below to ensure your fasteners are tightened

suffi ciently. To ensure your connections are correct, you should use an accurate, quality torque

wrench. It is highly recommended to go back over all fasteners and re-torque after fi ve days, and

every six months thereafter.

Table 2-1, Torque Values for Ground Busbar

Note: The ground busbar has different torque values for the small and large screws.

Wire Size

Busbar Screw Size Torque Values

10-32 [Small Screw]

5/16-24 [Large Screw]

#14 to #10 AWG

(2.1 to 5.3 mm

2

)

15 in. lbs. (1.7 N-m)

35 in. lbs. (4.0 N-m)

#8 AWG (8.4 mm

2

)

20 in. lbs. (2.3 N-m)

40 in. lbs. (4.5 N-m)

#6 AWG

(13.4 mm

2

)

25 in. lbs. (2.8 N-m)

45 in. lbs. (5.1 N-m)

#4 AWG (21.1 mm

2

)

NA

45 in. lbs. (5.1 N-m)

#3 to #1/0 AWG

(26.6 to 53.5 mm

2

)

NA

50 in. lbs. (5.6 N-m)

Table 2-2, Torque Values for the AC Terminal Blocks

Wire Size

Slotted M3.5 Screw Torque Values

#14 to #6 AWG

(2.1 to 13.4 mm

2

)

16 in. lbs. maximum

(1.8 N-m maximum)

Advertising