3. Start-up

Once line detection and optional classification stages are completed, the PSE must switch from low voltage to its
full voltage capacity (44-57 Volts) over a minimal amount of time (above 15 microseconds).
A gradual startup is required, as a sudden rise in voltage (reaching high frequencies) would introduce noise on the
data lines.
Once provision of power is initiated, it is common for inrush current to be experienced at the PSE port, due to the
PD’s input capacitance. A PD must be designed to cease inrush current consumption (of over 350 mA) within 50
ms of power provision startup.

4. Operation

During normal operation, the PSE provides 44-57 VDC, able to support a minimum of 15.4 watts power.

Power Overload

s

The IEEE 802.3af standard defines handling of overload conditions. In the event of an overload (a PD drawing a
higher power level than the allowed 12.95 Watts), or an outright short circuit caused by a failure in cabling or in the
PD, the PSE must shut down power within 50 to 75 milliseconds, while limiting current drain during this period to
protect the cabling infrastructure. Immediate voltage drop is avoided to prevent shutdown due to random
fluctuations.

5. Power Disconnection Scenarios

The IEEE 802.3af standard requires that devices powered over Ethernet be disconnected safely (i.e. power needs
be shut down within a short period of time following disconnection of a PD from an active port).
When a PD is disconnected, there is a danger that it will be replaced by a non-PoE-ready device while power is
still on. Imagine disconnecting a powered IP phone utilizing 48 VDC, then inadvertently plugging the powered
Ethernet cable into a non-PoE notebook computer. What’s sure to follow is not a pretty picture.
The standard defines two means of disconnection, DC Disconnect and AC Disconnect, both of which provide the
same functionality - the PSE shutdowns power to a disconnected port within 300 to 400ms. The upper boundary is
a physical human limit for disconnecting one PD and reconnecting another.

DC Disconnect
DC Disconnect detection involves measurement of current. Naturally, a disconnected PD stops consuming current,
which can be inspected by the PSE. The PSE must therefore disconnect power within 300 to 400 ms from the
current flow stop. The lower time boundary is important to prevent shutdown due to random fluctuations.

AC Disconnect
This method is based on the fact that when a valid PD is connected to a port, the AC impedance measured on its
terminals is significantly lower than in the case of an open port (disconnected PD).
AC Disconnect detection involves the induction of low AC signal in addition to the 48 VDC operating voltage. The
returned AC signal amplitude is monitored by the PSE at the port terminals. During normal operation, the PD's
relatively low impedance lowers the returned AC signal while a sudden disconnection of this PD will cause a surge
to the full AC signal level and will indicate PD disconnection.