2.0

Scope

System Setup describes receiving and handling of the Galaxy PW™ 100 to 225kVA, a description of major compo-
nents, the battery cabinet, and definition of the control panel indicators, which includes electrical, mechanical and
environmental specifications.

MGE also recommends obtaining an MGE field service engineer for final installation and basic startup for single and
parallel units.

CAUTION

Scheduling of the MGE Field Service Engineers typically should be done 7 to
10 days before they are required on-site. If the startup of the UPS is critical
to maintaining your schedule, please call the MGE toll free telephone number
at 1-800-438-7373 for assistance. The MGE Field Service Engineers will insure a
quick installation for the initial safe startup and configuration of your Galaxy PW™.

Final installation and start-up should be completed by a qualified MGE Field Service Engineer.

2.0.1

First steps by an on-site qualified Technical Engineer

Step 1.

Unpack and position the unit.

Step 2.

Connect the main (utility) power.

Step 3.

Connect the power circuits.

2.0.2

Final steps by MGE Field Service Engineer

Step 4.

Call MGE and wait for the MGE Field Service Engineer to complete the installation.

Step 5.

The MGE Field Service Engineer finalizes installation and the startup process.

Optional:

Procedure for temporary power prior to the final startup.

2.0.3

Required Equipment and Tools

The following equipment and tools are recommended for on-site installation:

Digital volt meter (DVM)

1/8 inch slotted screwdriver

Pallet jack/forklift

Conduit installation tools

Nut driver set

2 — 1