14.0

Changing Components

40

© Baxi Heating UK Ltd 2009

14.8

Gas Valve (Fig. 68)

1. Undo the nut on the gas feed pipe under the boiler.

2. Completely undo the securing screws and hinge the
facia panel down.

3. Disconnect the wires from the valve modulator and
the ignition lead from the spark generator. Disconnect
the pressure sensing pipe from the valve. Undo the
screw securing the spark generator electrical plug to the
valve and disconnect the plug.

4. Pull the earth wire off the spade terminal on the valve.

5. Remove the screws securing the inlet pipe flange to
the boiler bottom panel and those securing the outlet
manifold to the burner manifold.

6. Remove the valve from the boiler.

7. Note the orientation of the inlet pipe and outlet
manifold. Undo the securing screws and remove the
pipe and manifold.

8. Examine the ‘O’ ring seals for damage, replacing as
necessary.

9. Fit the inlet pipe and outlet manifold to the new valve,
ensuring that the ‘O’ ring seals are in place.

10. Reassemble in reverse order and check the burner
pressure (Section 11.2).

14.9

Temperature Sensor (Fig. 69)

1. Ease the retaining tab on the sensor away and
disconnect the electrical plug.

2. Unscrew the sensor from it’s pocket and reassemble
in reverse order. The plug will only fit one way.

14.10

Safety Thermostat

(Fig. 69)

1. Pull the electrical connections off the thermostat.

2. Remove the screws securing the thermostat to the
mounting plate on the flow pipe.

3. Reassemble in reverse order. The thermostat is not
polarised - either wire can fit either terminal on the
thermostat.

Gas Valve

Inlet Pipe

Gas Feed

Pipe

Electrical Plug

Temperature

Sensor

Safety Thermostat

Flow Pipe

Fig. 68

Fig. 69

Modulator

Wires

Ignition

Lead

Earth Wire